An open air in Berlin needs more than a good sound system. You have to clarify whether you may use the site, which authority is responsible, how loud you may be and when, and where the power comes from. Here you will find the responsible authorities, the applicable laws, the areas already approved and the contacts in all twelve districts. This text is not legal advice: what the responsible authority tells you is always binding.

Open air with Funktion One sound system at Fête de la Musique in Berlin

Stil vor Talent open air at Fête de la Musique

01. Where do you want to party?

Which permits you need depends above all on the site:

  • Private grounds, courtyard or roof terrace: You need permission from the owner or landlord. No special use permit is required, but noise protection still applies. If the event is public, i.e. open to everyone, you need a noise permit for disturbing music.
  • Public green space (park, meadow): Here you need at least two permits: an exemption under the Green Spaces Act from the Roads and Green Spaces Office and a noise permit from the Environment and Nature Conservation Office. This is how the Friedrichshain-Kreuzberg district office describes it in a reply to the Berlin House of Representatives.
  • Public road land (street, square, pavement): Here you need a special use permit and a traffic permit under § 29 StVO. Both are usually issued together. For music you also need the noise permit.
  • Venue with an outdoor area: Many Berlin venues already have the permits and their own conditions, such as fixed end times or level limits. Ask them in advance so that we can plan the system accordingly.

If the site is in a nature or landscape protection area, you also need the consent of the nature conservation authority.

02. Which authority is responsible?

Responsibility almost always lies with the offices of the district in which the site is located. Only for major events of citywide importance, such as the marathon or New Year's Eve, is the Senate administration responsible.

What Authority Legal basis Lead time
Event in a green space District Roads and Green Spaces Office § 6 (5) Green Spaces Act 6 to 8 weeks
Event on a street or square Roads and Green Spaces Office, in some districts the Public Order Office Special use under the Berlin Roads Act, § 29 StVO 8 to 9 weeks
Music and noise District Environment and Nature Conservation Office §§ 10, 11 LImSchG Bln, Event Noise Ordinance 4 weeks
Playing music in public GEMA Copyright before the event

Deadlines according to service.berlin.de and the Mitte and Pankow district offices. According to service.berlin.de, processing event applications takes 4 to 9 weeks on average.

What does the noise permit cost? For other public outdoor events the city quotes 100 to 1,500 €, for major events 400 to 7,000 €. The Berlin environmental protection fee ordinance is binding. For green spaces and road land there are also usage fees depending on duration and size. Non-profit organisers can be partially exempt.

What goes into the noise permit application? Location, date and schedule, expected number of visitors, distance to the nearest housing, setup, sound check, the loudspeakers with manufacturer and type and their positioning, as well as your noise protection measures. Also a justification of why the event should take priority over regular noise protection. You get the technical details of the system from us.

03. Which laws apply?

  • Green Spaces Act (GrünanlG), § 6: Green spaces may only be used in line with their purpose, and gently (para. 1). Since an amendment in 2021, the districts are to designate special areas to an appropriate extent for non-commercial art and cultural events (para. 2). Anything beyond that requires an exemption (para. 5).
  • Berlin Roads Act and StVO: Events on road land are a special use and require a permit. If traffic is affected, a permit under § 29 StVO is added. A passage of 3.5 to 5.5 metres must remain clear for the fire brigade.
  • Berlin State Immission Control Act (LImSchG Bln): It protects night-time quiet from 10 pm to 6 am as well as Sundays and public holidays. Public outdoor events with disturbing noise require a permit, other projects an exemption (§§ 10, 11). Anyone who holds an event without a permit or ignores conditions commits an administrative offence.
  • Event Noise Ordinance (VeranstLärmVo): It defines how noise from outdoor events is measured and assessed. Daytime is from 6 am to 10 pm, night-time from 10 pm to 6 am. During rest periods, such as 8 pm to 10 pm on weekdays, a surcharge of 6 dB applies. So-called disturbing events are limited to a maximum of 18 days a year at one location.
  • Administrative regulations on the LImSchG: There is no exemption for family celebrations and private parties. The normal limits apply there, which means night-time quiet from 10 pm.

04. Are there approved areas in Berlin?

Yes, but only a few, and you still need a permit. Approval only means that the authority considers the site suitable in principle.

  • Mitte: 24 vetted areas. In September 2026 the Mitte district office designated 24 public areas for non-commercial events, including Arkonaplatz, Genter Straße, Stephanplatz and Otto-Platz in Moabit, and Neues Ufer. Depending on the area, music is allowed during the day for up to 8 hours, up to 2 hours or not at all. No music is allowed at night, except in exceptional cases at Neues Ufer. For music the office usually requires level calibration: an accredited measuring body sets a sound limiter, which according to the district costs over 1,000 €. You submit the application 8 weeks in advance for road land and 6 weeks for green spaces.
  • Friedrichshain-Kreuzberg: Gleisdreieck Park. In July 2026 the district assembly approved an area in Gleisdreieck Park for free, non-commercial open airs, the first district in Berlin to do so. Assessments are still pending before the first test events.
  • Tegel model site: On the Frachtkante grounds at the former Tegel Airport there is a model site intended specifically for events. Open airs have been held there since April 2026. Clubcommission is involved in the project.
  • Other districts: Here every event is assessed individually. In response to a query in the House of Representatives, several districts reported that they had not designated any areas; Marzahn-Hellersdorf, for example, sticks to case-by-case assessment. Ask the Roads and Green Spaces Office whether areas have been designated in the meantime.

Background: back in 2021 the Senate prepared 13 areas for open-air culture with the "Draußenstadt" programme. Clubcommission searched for the areas at the time.

Crowd at 72 HOURS May Day Open Air in Berlin

72 HOURS May Day Open Air in a Berlin courtyard

05. Clubcommission and the Free Open Air Initiative

Clubcommission is the network of Berlin club culture. With its Free Open Air Initiative it has been campaigning since 2013 for non-commercial open airs to be able to take place legally. According to Clubcommission, free open airs are self-organised outdoor music and culture events with free admission, where artists and organisers receive nothing or only cost reimbursement.

  • Advice: Clubcommission offers advice to organisers, available via beratung@clubcommission.de. The initiative itself can be reached via freeopenair@clubcommission.de.
  • Workshop: Once a year there is a Free Open Air Workshop with experts, most recently in March 2026. Topics include the legal framework, knowledge exchange and an infrastructure exchange.
  • Tools: On clubcommission.de you will find checklists, handbooks and concepts on awareness, safety and nature conservation.
  • Political work: A legal opinion commissioned by Clubcommission concluded in 2025 that the districts are obliged to designate areas under the Green Spaces Act. It also proposes a general ruling and fee-free permits for non-commercial open airs.

For planning, Raumsonde Berlinis also worthwhile: the platform by Kollektiv Spieltrieb e.V. has an interactive map, an application pre-check and a site plan tool.

06. The process step by step

  1. Find a site: Check whether there is an approved area, and avoid places with a history of conflict or nature reserves.
  2. Sound out the district: Ask the Roads and Green Spaces Office who is responsible and what is possible. A quick call saves weeks.
  3. Prepare a concept: Site plan, safety concept, waste concept, awareness team, number of visitors and schedule. Clubcommission advises bringing solutions for noise, neighbours, waste and safety from the start.
  4. Submit applications: Special use or exemption at the Roads and Green Spaces Office, 6 to 9 weeks in advance. Noise permit at the Environment and Nature Conservation Office, at least 4 weeks in advance. Plus liability insurance and GEMA registration.
  5. Make compromises: The authority often requires different times, a smaller area or level calibration. Stay friendly and persistent.
  6. Keep the permit on site: Police and the Public Order Office may ask to see it at any time.
  7. Return the site clean: The organiser pays for damage to grass or trees.

07. Contacts in the districts

The Environment and Nature Conservation Office is responsible for noise protection, the Roads and Green Spaces Office (in some districts the Public Order Office) for the site.

District Noise protection Site / event
Charlottenburg-Wilmersdorf 030 9029-18801 (contact form) Public Order Office: ordnungsamt@charlottenburg-wilmersdorf.de, 030 9029-29000
Friedrichshain-Kreuzberg 030 90298-4412 (contact form) Roads and Green Spaces Office, via berlin.de/ba-friedrichshain-kreuzberg
Lichtenberg 030 90296-4230 Public Order Office: ordnungsamt-zab@lichtenberg.berlin.de, 030 90296-4310
Marzahn-Hellersdorf umweltschutz@ba-mh.berlin.de, 030 90293-6701 SGA-Strassen@ba-mh.berlin.de, 030 90293-7500
Mitte post.umwelt-naturschutzamt@ba-mitte.berlin.de, 030 9018-23054 veranstaltungen@ba-mitte.berlin.de, 030 9018-22823
Neukölln umweltamt@bezirksamt-neukoelln.de, 030 90239-0 sondernutzung@bezirksamt-neukoelln.de, 030 90239-2181
Pankow umwelt-natur@ba-pankow.berlin.de, 030 90295-7860 sondernutzung@ba-pankow.berlin.de, 030 90295-0
Reinickendorf umweltamt@reinickendorf.berlin.de, 030 90294-5149 Public Order Office: ordnungsamt@reinickendorf.berlin.de, 030 90294-2933
Spandau umwelt@ba-spandau.berlin.de, 030 90279-3888 sga@ba-spandau.berlin.de, 030 90279-2721
Steglitz-Zehlendorf post.umnat@ba-sz.berlin.de, 030 90299-7319 Roads and Green Spaces Office, via berlin.de/ba-steglitz-zehlendorf
Tempelhof-Schöneberg umwelt@ba-ts.berlin.de, 030 90277-4490 sondernutzung-sga@ba-ts.berlin.de
Treptow-Köpenick naturschutzamt@ba-tk.berlin.de, 030 90297-5932 Public Order Office: ordnungsamt@ba-tk.berlin.de, 030 90297-4629

As of November 2026, according to service.berlin.de and the district offices. For major events of citywide importance: Senate administration, veranstaltungslaerm@senmvku.berlin.de, 030 9025-2264.

08. How loud may it be?

Night-time in Berlin is from 10 pm to 6 am. After that, much stricter values apply, which is why most open airs turn down or end at 10 pm. How loud it may be during the day depends on the surroundings and is set out in the conditions of your permit. Measurements are taken not on the dance floor but at the nearest housing. With the right technology you can do a lot to make it sound good on site while staying quiet in the neighbourhood:

  • Point loudspeakers away from residential buildings and place them closer to the dance floor.
  • Several smaller loudspeakers instead of two large stacks at full power.
  • Control the bass: with a cardioid or end-fire subwoofer arrangement, the bass stays at the front and gets quieter towards the back. We explain this in our guide Setting up the subwoofer and in the video on bass arrangements.
  • Measure and document levels if the permit sets limits. For level calibration by a measuring body, we set up the system beforehand exactly as it will run on the day.

Rent a PA system in Berlin: Funktion One stack at an open air

09. Power outdoors

There is usually no power connection on an open-air site. The power therefore comes from a power station or a generator. A sound system for 100 to 150 guests needs around 1.5 to 2.5 kW, for 200 guests about 3.5 kW. Lighting and DJ equipment come on top.

Rent EcoFlow DELTA Pro 3 power station for open airs
Rent Scheppach iGT 3500 generator for open airs
  • power station: Silent and without exhaust fumes. The best choice for smaller setups and sites close to residential buildings. Plan the battery capacity according to power and running time; for longer events with several units or recharging.
  • Generators: Supplies power for many hours, but is audible. Place it as far away from the dance floor and neighbours as possible. In the noise permit application, the authority explicitly asks about quiet generators as a protective measure.
  • Secure cables: Over walkways, place cable ramps on top of the cables.

We calculate exactly how much power you need in our guide Power at events .

10. Weather and equipment

  • Rain protection: DJ booth, mixing desk and power supply belong under a roof or tent. Loudspeakers tolerate light rain better than electronics.
  • Lighting for outdoors: Battery-powered fixtures such as the Astera AX5 set need no cables, and the BeamX.7 Outdoor are built for outdoor use.
  • Wind: Secure speakers on stands, and only place large stacks on firm, level ground.
  • Sun: Don't leave mixers and players in direct sunlight for hours.

11. Checklist: what should be done when

  • 10 to 12 weeks before: Secure the site and date, ask the district which permits are needed. Use Clubcommission's advice if you have questions.
  • 8 to 9 weeks before: Submit the application to the Roads and Green Spaces Office, take out insurance.
  • 4 to 6 weeks before: Submit the noise permit application, register with GEMA, reserve equipment and power.
  • 2 weeks before: Clarify access, setup times, waste, toilets and rain plan, and if needed the date for level calibration.
  • On the day: Have the permit with you, setup and sound check before admission, keep an eye on levels, turn down at 10 pm.

For summer parties we offer our summer party packages with delivery and setup; for larger open airs we plan a Funktion One system to suit the site and the neighbourhood.

Sources:

Questions about your site? Write to us or call: 030 2000 5443.